Most builders have their own ‘just sign here’ standard build terms. They vary enormously in length and complexity. Such agreements often miss out important aspects and can be subject to local law and jurisdiction - whose courts may not be impartial and where you may struggle to find competent, specialist lawyers. Don’t sign them. Contact us for guidance. Given the amount of money at stake, such contracts should only be viewed as an opening to contractual negotiations.

minutes

10

Reading time

10 May 2023

Last revised

Most builders have their own ‘just sign here’ standard build terms. They vary enormously in length and complexity. Such agreements often miss out important aspects and can be subject to local law and jurisdiction - whose courts may not be impartial and where you may struggle to find competent, specialist lawyers. Don’t sign them. Contact us for guidance. Given the amount of money at stake, such contracts should only be viewed as an opening to contractual negotiations.

  • Privacy concerns and the need for NDAs should be addressed early on with the engagement of an experienced lawyer.

  • Payments should be made upon completion of build milestones, with independent surveyor signoff, and account for material costs, transport, and exchange rates.

  • Security measures should be in place to protect against builder insolvency, including ownership transfer and guarantees from the builder's bank.

  • Consider local legal requirements for ownership transfer and potential statutory liens by unpaid subcontractors.

  • Clearly define the triggering events and duration of guarantees to ensure protection in case of builder insolvency or yacht issues.

  • Establish clear and rigid procedures for change orders to avoid cost overruns and delays.

  • Subcontractors should be carefully vetted, and the builder should remain liable for their mistakes. Materials should not be subject to title retention.

  • Specify insurance requirements for the part-built project and ensure the wording is adequate and obtained from reputable insurers.

  • Address force majeure events, their effect on the delivery date, and the need for a cap. Clarify buyer-ordered modifications' impact on delays.


  • Ensure all correct legal documents for the yacht's registration are presented before final payment and agree on the place of legal delivery.

  • Allow access for tests, inspections, and reasonable rectification of faults before delivery. Define criteria for acceptance or rejection of the yacht.

  • Formal testing at sea is necessary to verify performance against specifications, and a margin of tolerance with incremental compensation may be agreed upon.

  • Establish the buyer's right to refuse delivery if faults are not rectified, and differentiate between minor non-conformities and deliverable condition requirements.

  • Warranty period should be agreed upon for materials and workmanship, and provisions for rectifying defects and compensation should be addressed.

  • Dispute resolution mechanisms should include independent technical experts for technical matters and arbitration or litigation for non-technical or high-value disputes.

  • Consider enforceability and confidentiality aspects when choosing between arbitration and litigation.

  • Ensure all correct legal documents for the yacht's registration are presented before final payment and agree on the place of legal delivery.

  • Allow access for tests, inspections, and reasonable rectification of faults before delivery. Define criteria for acceptance or rejection of the yacht.

  • Formal testing at sea is necessary to verify performance against specifications, and a margin of tolerance with incremental compensation may be agreed upon.

  • Establish the buyer's right to refuse delivery if faults are not rectified, and differentiate between minor non-conformities and deliverable condition requirements.

  • Warranty period should be agreed upon for materials and workmanship, and provisions for rectifying defects and compensation should be addressed.

  • Dispute resolution mechanisms should include independent technical experts for technical matters and arbitration or litigation for non-technical or high-value disputes.

  • Consider enforceability and confidentiality aspects when choosing between arbitration and litigation.

  • Privacy concerns and the need for NDAs should be addressed early on with the engagement of an experienced lawyer.

  • Payments should be made upon completion of build milestones, with independent surveyor signoff, and account for material costs, transport, and exchange rates.

  • Security measures should be in place to protect against builder insolvency, including ownership transfer and guarantees from the builder's bank.

  • Consider local legal requirements for ownership transfer and potential statutory liens by unpaid subcontractors.

  • Clearly define the triggering events and duration of guarantees to ensure protection in case of builder insolvency or yacht issues.

  • Establish clear and rigid procedures for change orders to avoid cost overruns and delays.

  • Subcontractors should be carefully vetted, and the builder should remain liable for their mistakes. Materials should not be subject to title retention.

  • Specify insurance requirements for the part-built project and ensure the wording is adequate and obtained from reputable insurers.

  • Address force majeure events, their effect on the delivery date, and the need for a cap. Clarify buyer-ordered modifications' impact on delays.


superyacht yacht megayacht for sale charter newbuild build building construction owner ownership owners club owner's owners' broker brokerage build agreement yard
superyacht yacht megayacht for sale charter newbuild build building construction owner ownership owners club owner's owners' broker brokerage build agreement yard

An immediate concern usually not covered is privacy, which may, of course, be one of the reasons you’re looking to have a yacht built in the first place. An experienced lawyer must be engaged at the outset – not brought in at the last minute to cast an eye over what everyone else considers to be a done deal. And his or her priority will be to get NDAs in place with the builder.

SPECIFICATION & COST


There’s no point finding designers who pen the perfect yacht, which the builder then interprets in its own (possibly cost-cutting) way. Moreover, modifying a yacht retrospectively can be particularly time-consuming and expensive. An incorrectly interpreted specification might prevent a yacht being chartered out. So the design and specification, in compliance with specific Flag State regulations and classification society Rules (if applicable) must be set out in exquisite detail, and agreed – in principle – with the builder, along with the build cost. With this settled, attention can be turned to the principal elements of the build agreement.


PAYMENTS


It’s customary for payments to be made upon the completion of certain build milestones. This way, your exposure is minimised while the builder has sufficient cashflow. Whether or not a stage has been satisfactorily completed is a technical question, needing signoff from an independent surveyor instructed by you – not the builder. The first payment is made by way of a deposit before construction starts.


With large projects taking years to complete, account should be made for fluctuations in materials costs and transport, and exchange rates. Placing the builder under real financial strain will be to no one’s advantage.


SECURITY


Consideration must be given to the consequence of the builder folding mid-build. It happens. Without agreement otherwise, the builder would be left with both instalments and an incomplete yacht as assets, with you standing at the end of a long line of creditors. So your security takes two forms. Firstly, ownership of the yacht is transferred to the buyer as it is built. Secondly, the builder supplies the buyer with guarantees, issued by the builder’s bank, for the refund of pre-delivery instalments, against which the buyer pays each such instalment. Such guarantee can also take the form of an insurance-backed Advance Payment Bond (remembering that banks can, on occasion, themselves go bust).


Keep in mind that any transfer of ownership may be subject to formalities under local law – regardless of the build agreement’s law and jurisdiction – so it’s important to take local legal advice. If the worst does happen, in spite of all the financial due diligence you undertook, then you will still need to have the project moved elsewhere for completion, so check that, under local law, unpaid subcontractors aren’t automatically entitled to a statutory lien over the yacht and materials, which may prevent removal.


It is vital to state in the contract that only ownership, and not risk (which may otherwise also automatically be transferred at the same time), is being transferred. If the yacht is being financed, it may also be possible to register a mortgage over the incomplete project in favour of the lender.


As to the specific small print of the guarantee, the most important element is what triggers the ability of the buyer to make a demand for payment under it. The most favourable option is for the buyer to have the ability to make a demand by stating that there has been a default on the part of the builder, under the terms of the build agreement, which therefore merits payment. The builder or bank may wish instead to expressly state the particular events which could lead to payment.


By far the most important triggering event which must be described in the guarantee is the builder’s insolvency. It will not be good enough, for example, for the guarantee to become payable only when a receiver has been appointed, or any dispute between buyer and builder is settled, as these may take many months or even years in some jurisdictions. Far better for the guarantee to become payable as soon as it can be shown that the builder is in financial difficulties. Moreover, the procedure for presenting the bank with a demand for payment should be simple and straightforward.


And there’s no point in having a guarantee which offers high protection, but which expires too soon. Where a guarantor will only pay after the matter has been litigated (in the absence of settlement) the guarantee must last for a period of years to take account of lethargic court processes. A number of owners have, in the past, enjoyed using their own business acumen to diagnose mismanagement and their own capital to save it. But this takes time and may not lead to a solution.


Moreover, if the builder survives until completion of the yacht, there may still be issues with the delivered yacht for which the buyer wants significant compensation, and may still need the protection of the guarantee. If it expires immediately upon delivery and sea trial, for example, then there will be virtually no time in which to decide whether or not demand payment, and calculate the appropriate figure.


CHANGE ORDERS


It may well be that it’s only when you see your yacht start to take shape that realise that the layout or specification could be improved. While there’s a temptation to discuss modifications orally – for convenience – cost overruns and disproportionate delays may result.


Modification procedures must be clear, and rigidly adhered to. As large numbers of changes may also start to affect the builder’s other projects, the builder may want terms in the contract to the effect that such modifications will only take effect if the builder agrees to the proposed adjustment to the contractual price and delivery date. The builder may also want to reserve a right of refusal if other projects would be affected. Additional payments may also be required. Clearly, the builder could be put in an overly dominant position if such a clause was not well drafted.


In the case of very large projects taking many years, you may also want to leave gaps in the specification to allow for last-minute choices of high-tech equipment.


SUBCONTRACTORS


It’s common to subcontract significant elements of the builds, but you must make sure that only approved third parties can be brought in. If there’s any doubt, ask your project manager to visit the subcontractors and their previous projects to assess quality.


To avoid confusion, the builder should still be expressly liable for any of its suppliers' or subcontractors' mistakes. Further, the builder must be obliged to pay suppliers promptly, and the materials provided must not be allowed to be subject to any form of title retention – to prevent anything being reclaimed later.


DAMAGE


While the builder should be obliged to insure the part-built project, the quality and wording of that insurance must also be clearly specified if it’s to be worth more than the paper it’s written on. The Institute Clauses for Builders’ Risks policy wording is adequate, and security obtained on the Lloyd’s of London insurance market (or equivalent) should be insisted upon. The builder and buyer should be named as joint assured, with any claims payable to the builder and buyer as a reflection of their interests at the time of the claim.


There will also be other matters to be considered in the event of the project being damaged. You should have the option of either cancelling the contract and being refunded payments made up to that point, or requiring the builder to use its insurance payout to carry on with the build, in spite of the enormous delays involved.


Where the damage causes the project to be scrapped rather than just delayed, builders will normally be reluctant to agree to compensate buyers for the loss of their slot, and for any premium a speculative buyer hoped to make on the build. It is still open to buyers to seek separate insurance for this loss. A new delivery schedule will need to be agreed.


FORCE MAJEURE


Events beyond the control of the builder are known as ‘force majeure’ events. These may or may not be defined by law. Where they are not, the parties need to ensure that all possibilities are covered, and what their effect will be. Typically, the contractual delivery date will be extended, but the parties will need to clarify whether this is by reference to the number of days the force majeure event continued or the effect on the project’s critical path. Even where delay is caused by a force majeure, such latitude should be subject to a cap – so that the point where enough is enough is clear. The exception to this will be delays due to modifications ordered by the buyer.


DELIVERY


Sorting matters out with a builder after the final instalment has been paid can be especially difficult. It is crucial that all the correct documents relating to legal title are presented before payment is made. Otherwise the new yacht cannot be registered and will not be allowed to sail anywhere. The place of legal delivery may also have tax implications, and must be agreed.


At the point of delivery, the yacht should not only function and appear as envisaged, but it should meet all the classification society and Flag State regulations, especially if it is going to be chartered. Build agreements should allow not only access to the builder for the buyer’s representative, but reasonable tests and inspections, including those to be undertaken at subcontractors’ and suppliers’ premises. The representative should be allowed to require the builder to rectify evident faults immediately.


TESTING


The newly completed yacht will have to be formally tested, at sea, to make sure that the performance matches the specification. This is the buyer’s opportunity to determine whether the yacht has been built in conformity with the agreed contractual specifications and meets the contractual performance criteria. The owner’s representative, Class and Flag State surveyors will attend these trials and sign off the individual test protocols.


As no two yachts are ever identical, their performance in terms of displacement, speed, noise levels, vibration and range, are difficult to predict even whilst using the latest computer-aided design techniques, FEA (finite element analysis), CFD (computational fluid dynamics), tank testing and wind tunnel testing. A practical solution is to agree a small margin of tolerance followed by incremental compensation which the builder must pay if the performance criteria aren’t met but still fall within certain limits. This incremental approach can only be applied to a certain extent and thereafter the right of rejection must lie with the buyer.


REJECTION


Ultimately, if faults are not put right, the buyer must have the right to refuse delivery. So the build agreement must make it crystal clear whether a particular requirement is to have the legal status of a condition, entitling the buyer to refuse delivery – especially as small defects are simply inevitable in any large project. The laws of most jurisdictions are vague on such matters, involving considerations of whether the yacht is of ‘satisfactory quality’ and ‘reasonably fit’ for purpose, and therefore in a ‘deliverable’ condition. This problem is made much worse by the critical importance of aesthetic elements. The standard contractual term for the small and inevitable defects is a ‘minor non-conformity’. Usually, the buyer will be forced to accept delivery with the minor non-conformity list outstanding, under the proviso that the list is taken care of by the builder as soon as possible.


WARRANTY


Not all of your new yacht’s inevitable little faults will come to light during the trails. Only over time will all the equipment and systems be used in varying weather conditions. The builder should guarantee materials and workmanship for a period of warranty – at least a year – after delivery. Builders will usually agree to correct defects during this period, but not to compensate. The builder may demand that otherwise pre-existing legal rights are given up, and that once the warranty period has expired no further responsibility will rest with the builder.


The builder may not wish to compensate for loss of use and charter income, and a detailed notification procedure may also have to be complied with. Such demands should be considered carefully. Where significant concessions are granted by the buyer, the contract should ideally provide for the last payment instalment to be withheld until the end of the warranty period. It may be necessary to bring the yacht into dry-dock, so the buyer must be entitled to have work carried out by a yard other than that in which she was built if cruising schedules are not going to be spoiled..


DISPUTES


Disputes between the buyer and builder are most likely to be technical in nature. Even the lustre of paint, for example, can be objectively measured. As courts are better at deciding points of law rather than fact, it makes sense to decide which points would be better decided by an independent expert. A representative from the classification society, for example, is typically agreed on to decide points upon which the society has created technical rules, but the use of another mutually agreed third-party expert should also be agreed for other matters.


The expert should be asked to provide an independent opinion, and not act as arbitrator. Arbitrators can decide upon matters of law and evidence, and this requires the expertise of an experienced legal expert. Matters which are non-technical, or which involve large sums, should be agreed to be arbitrated according to the rules of an established arbitrators’ association, or referred to court. The choice of arbitration or litigation may depend on the enforceability or otherwise of an arbitrator’s decision, compared with a court judgment, in the home states of the parties involved. Sometimes, an arbitrators’ decision will be the more powerful of the two, and – unlike court proceedings – arbitrations are confidential in nature.


To include long-term flexibility, and an acceptance that some flaws will be evident in the finished product, into a cast-iron contract, is no easy task. Time spent discussing and agreeing on this at the start will be a sound investment compared with the potential arguments which bubble-up later on.

superyacht yacht megayacht for sale charter newbuild build building construction owner ownership owners club owner's owners' broker brokerage build agreement yard

Thank you to all our Members who contributed to this article. Unless otherwise stated, this article broadly describes, by way of illustration, the situation in the United Kingdom waters in respect of United Kingdom-registered vessels.  This piece does not provide or replace legal advice.

Questions or comments?

Please contact us

You can also read about

Join the discussion over in

the Club's                  group

Questions or comments?

Please contact us

You can also read about

bottom of page