Building a large, custom yacht is a complex process which must be carefully choreographed. There are a lot of specialists involved, and much which can wrong. Here we look at what construction actually involves, and why building your team at the outset is such a vital first step.
minutes
4
Reading time
10 May 2023
Last revised
Building a large, custom yacht is a complex process which must be carefully choreographed. There are a lot of specialists involved, and much which can wrong. Here we look at what construction actually involves, and why building your team at the outset is such a vital first step.
Large yacht construction involves a tightly-controlled sequence of events, and adherence to classification society standards for welding and quality control.
Machinery and larger systems must be installed before the superstructure is joined ot the hull.
Filling, fairing, insulation, and the addition of cable trays and pipework must be carefully choreographed.
Interior panels are prefabricated and should be removable for access and maintenance.
The sooner the build captain is recruited the better.
Project managers should be present at all stages of the build and provide progress reports.
Crewmembers, other than the build captain, are engaged as the build nears completion, with the build captain overseeing recruitment.
Insurance coverage should be clarified in the build agreement, including employer's liability insurance for crew.
Sea trials are conducted to test the yacht's systems and performance, followed by formal legal delivery and a warranty period to address any issues that arise.
Project managers should be present at all stages of the build and provide progress reports.
Crewmembers, other than the build captain, are engaged as the build nears completion, with the build captain overseeing recruitment.
Insurance coverage should be clarified in the build agreement, including employer's liability insurance for crew.
Sea trials are conducted to test the yacht's systems and performance, followed by formal legal delivery and a warranty period to address any issues that arise.
Large yacht construction involves a tightly-controlled sequence of events, and adherence to classification society standards for welding and quality control.
Machinery and larger systems must be installed before the superstructure is joined ot the hull.
Filling, fairing, insulation, and the addition of cable trays and pipework must be carefully choreographed.
Interior panels are prefabricated and should be removable for access and maintenance.
The sooner the build captain is recruited the better.
Generally speaking, yachts are far more complex than working vessels of a similar size, and finishes must, of course, be of a far higher standard. Yard cleanliness and orderliness make ensuring this much easier. You’ll have gotten a feel for the builder’s work practices having visited beforehand. Once the build is underway, there’s a lot going on and a lot to go wrong. For steel-hulled yachts, huge plates are cut to shape before being assembled and welded into place. Steps must be taken in precisely the right order. Where the vessel will be classed, welders must be qualified in accordance with the classification society standards. The welds themselves must conform to measurable standards with tolerances measuring less than a millimetre. If it’s not right it must be corrected until it is.
It can take a year and half to complete a bare 100-metre hull, during which about 1,000 tonnes of steel will be used. Superstructures are typically made from aluminium – requiring even greater welding skills. They are usually constructed in sections, away from the hull, then bonded together. Larger items of machinery, such as engines and generators, must be installed before superstructure encloses the internal spaces. The project will then typically be moved way from under the gantry cranes of the construction facility, to a fitting-out facility, where the machinery and systems will be fitted.
The hull’s surface will be slightly rippled and will need filling and fairing: a skilled and labour-intensive process. The epoxy fillers, and paints covering them, are sensitive to temperature and humidity. Insulation, cable trays and pipework can now be installed – in exactly the right sequence. Interior panels are normally prefabricated by subcontractors, before being brought to the yard for installation. They will normally produce full-scale mock-ups of various interiors which you can check before they are installed. It’s important that the bulkhead and deckhead panels be removeable to allow access as needed for regular system maintenance. It's vital that photographs are taken during construction so that what’s behind the panels can be checked easily.
SUPERVISION
The builder will employ its own project manager(s), but with so much going on it’s easy to see why your project manager needs to be present at all stages of the build. Your project manager should compile monthly reports showing progress, with photos and detailing how this compares to the agreed time schedule. Your project manager should also know the build agreement inside-out, and must remind you of upcoming decision deadlines in good time. As with any large project, communication is key.
ENGAGING CREW
More and more crew are brought in as the build nears completion. The build captain is first – and in the case of larger projects may have been engaged at the outset. Where the build is on a more modest scale, the project manager also performs the role of build captain and may be the vessel’s first captain following launch. Build captains perform two roles: firstly they add a helpful seagoing captain’s perspective to the build, and secondly they recruit and oversee other crewmembers.
The build captain will need excellent organisational skills, an analytical mindset and be a superb manager and motivator. Next comes the Chief Engineer, who can bring real value right away, followed by other heads of departments, who will be key in recruiting those who report to them – and may already have contacts waiting in the wings. Some hires may have been misjudged and just aren’t the right fit. This is to be expected. Not hiring crew until absolutely necessary can be a false economy. There’s much to be got ready before launch. Aside from completing the build, operational and regulatory procedures need to be established, and if these are rushed they may not be fit for purpose.
INSURANCE
The build agreement should be clear on when the build no longer bears the risk of damage occurring to the yacht, or the liabilities incurred to third parties. There should be no gaps in cover. Keep in mind, too, that you will need employers’ liability insurance in respect of crew as soon as they are engaged. While insurance brokers owe a legal duty to you, as insured, in reality they can value their commercial relationships with underwriters more. Indeed, some will expressly be your agent at the time of inception, but become the underwriter’s agent once a claim has been made. Be warned, and examine the policies in detail.
TRIALS
At last, your new yacht is complete and is ready for her first sea trial. You may like to come along – but it’s not going to be the most exciting cruise. Before she goes anywhere, there’s a dock trial. The generators and main engines are started and their cooling systems checked for leaks. Once the captain is satisfied that she is ready, she can head out to sea. Aboard will be representatives from the builder, subcontractors and classification society, as well as your own team. All kinds of objective measurements are made which can be checked against the contractual specification. The trial will take most of the day, or a few days for a large, complex vessel.
DELIVERY
At last your yacht is ready for formal, legal delivery. There may still be teething problems evident at the time of delivery, which the builder hasn’t had time to correct, but which you’re happy to live with for now. The scope and nature of such works must be formally agreed. The build documentation will have been examined and approved by your lawyer, and will be released to you against receipt of the penultimate payment – the final payment being made upon successful completion of the warranty period.
WARRANTY PERIOD
Because yachts are, in essence, a matrix of complex systems operating together in a harsh environment, it is inevitable that some systems will fail, or fail to perform as expected. The warranty period should be clearly set out in the build agreement. It is vital for crewmembers to inform the captain, and the captain to inform you and the builder, right away and in writing, of any faults. Documentation and record keeping are key. Keep in mind any notice formalities which must be observed.
It's in the builder’s interests to work with you to create a yacht which will serve as a masterpiece – quite literally a shining example of what that yard is able to produce. Finding new clients is expensive and time-consuming. It’s far easier to keep existing clients happy and work towards selling them a larger yacht.